name: Analyze Feature Dependencies
description: Map feature dependencies and suggest optimal implementation order
author: Dependency Analysis Engine
version: 1.0.0
tags: [prd, dependencies, planning, implementation, order]
---

# Feature Dependency Analysis

## Overview
Analyze PRD features to identify dependencies, blockers, and parallel work opportunities. Generate implementation order recommendations with critical path analysis.

## Instructions

### Step 1: Locate and Read PRD

```bash
# Expected location
docs/PRD.md
```

If not found, ask user for PRD location.

### Step 2: Extract Features

Parse YAML frontmatter `features` array:

```yaml
features:
  - name: "User Authentication"
    complexity: "medium"
    priority: "p0"
    requires: ["biometric_auth", "mfa"]
  - name: "Dashboard"
    complexity: "medium"
    priority: "p0"
    requires: ["real_time_updates", "data_visualization"]
```

Also extract from PRD body if features have expanded descriptions with:
- User stories
- Technical requirements
- Acceptance criteria

### Step 3: Identify Dependency Types

**1. Technical Dependencies (BLOCKING)**
These MUST be implemented first:

- **Authentication → All Features:**
  - Any feature requiring user identity depends on auth
  - Keywords: "user-specific", "personalized", "profile", "account"

- **Database Schema → CRUD Features:**
  - Data models must exist before features using them
  - Keywords: "save", "retrieve", "update", "delete", "store"

- **API Foundation → API-Dependent Features:**
  - Backend endpoints required before frontend consumption
  - Keywords: "fetch from server", "API call", "REST endpoint"

- **Payment Integration → Monetization:**
  - Stripe/PayPal setup blocks checkout, subscriptions, billing
  - Keywords: "payment", "checkout", "billing", "subscription"

- **Search Infrastructure → Search Features:**
  - Elasticsearch/Algolia needed before search UI
  - Keywords: "search", "find", "filter", "query"

**2. Logical Dependencies (STRONGLY RECOMMENDED)**
Should be implemented in order, but can be worked around:

- **Core Entity → Related Entities:**
  - Example: "Product" before "Product Reviews"
  - Example: "User Profile" before "User Preferences"

- **Create → Read/Update/Delete:**
  - Must be able to create entities before managing them

- **Basic Feature → Advanced Feature:**
  - Example: "Text Chat" before "File Sharing in Chat"
  - Example: "Product List" before "Product Comparison"

**3. Domain Dependencies (RECOMMENDED)**
Best practice ordering:

- **Compliance Foundation → Data Features:**
  - Encryption, audit logs before handling PHI/PII
  - Keywords: "HIPAA", "PCI-DSS", "sensitive data"

- **Offline Support → Online Features:**
  - Sync infrastructure before features using it
  - Keywords: "offline", "sync", "local storage"

- **Real-time Infrastructure → Live Features:**
  - WebSocket/Firestore setup before live updates
  - Keywords: "real-time", "live", "instant", "push"

**4. No Dependencies (PARALLEL)**
Can start immediately and work in parallel:

- UI-only features with mocked data
- Design system / component library
- Static content pages (About, Help, FAQ)
- Analytics setup
- Error tracking setup

### Step 4: Analyze PRD Features

For each feature, determine:

1. **Direct Dependencies:** What must exist before this?
   - Look for `requires` field in YAML
   - Analyze feature description for keywords
   - Check technical requirements

2. **Reverse Dependencies:** What depends on this?
   - Which features need this one?

3. **Complexity Score:** From YAML (`low`/`medium`/`high`/`critical`)

4. **Priority:** From YAML (`p0`/`p1`/`p2`)

5. **Can Start When:**
   - Immediately (no deps)
   - After [Dependency] complete
   - After [Dependency] started (parallel)

### Step 5: Build Dependency Graph

Create adjacency list:

```
User Authentication
  ├─ Depends on: [None]
  └─ Blocks: [Dashboard, Profile, Settings, ...]

Dashboard
  ├─ Depends on: [User Authentication, Real-time Infrastructure]
  └─ Blocks: [Dashboard Widgets, Notifications]

Payment Integration
  ├─ Depends on: [User Authentication, Product Catalog]
  └─ Blocks: [Checkout, Subscriptions, Invoices]
```

### Step 6: Identify Critical Path

**Critical Path** = Longest sequence of dependent features

Algorithm:
1. Start from features with no dependencies
2. Calculate total time to complete each feature + all its dependencies
3. Feature with longest path = critical path

```
Critical Path Example:
Authentication (2 weeks)
  → Product Catalog (3 weeks)
    → Shopping Cart (2 weeks)
      → Payment Integration (4 weeks)
        → Checkout (2 weeks)
          = 13 weeks total (critical path)

Parallel path:
User Profile (1 week) → Settings (1 week) = 2 weeks (non-critical)
```

### Step 7: Recommend Implementation Phases

**Phase 1 - Foundation (Weeks 1-4)**
- No-dependency features
- Critical path starters
- Infrastructure setup

**Phase 2 - Core Features (Weeks 5-12)**
- P0 features dependent on Phase 1
- Critical path middle sections

**Phase 3 - Advanced Features (Weeks 13-20)**
- P1 features
- Features with multiple dependencies

**Phase 4 - Polish (Weeks 21-24)**
- P2 features
- Nice-to-haves
- Performance optimization

### Step 8: Generate Dependency Report

Create `docs/FEATURE_DEPENDENCIES.md`:

```markdown
# Feature Dependency Analysis: [Project Name]

**Generated:** [Date]
**Source:** docs/PRD.md
**Total Features:** [Count]

---

## Executive Summary

| Metric | Value |
|--------|-------|
| 🎯 Total Features | XX |
| 🔴 P0 Features | XX |
| 🟠 P1 Features | XX |
| 🚀 Can Start Immediately | XX |
| 🔗 Blocking Features | XX |
| ⏱️ Critical Path Duration | XX weeks |
| 🔀 Parallel Work Streams | X |

**Key Insight:** [Most impactful finding, e.g., "Payment Integration is on critical path - any delay cascades to 5 downstream features"]

---

## Dependency Graph

### Visual Representation

```
                    ┌─────────────────────┐
                    │ Authentication (P0) │
                    │   Medium - 2 weeks  │
                    └──────────┬──────────┘
                               │
                 ┌─────────────┴──────────────┐
                 │                            │
        ┌────────▼────────┐        ┌────────▼────────┐
        │  Dashboard (P0) │        │ User Profile    │
        │  Medium - 3w    │        │   Low - 1w      │
        └────────┬────────┘        └─────────────────┘
                 │
        ┌────────▼────────┐
        │ Product Catalog │
        │   High - 4w     │
        └────────┬────────┘
                 │
    ┌────────────┴────────────┐
    │                         │
┌───▼──────────┐    ┌────────▼────────┐
│ Shopping Cart│    │ Wishlist (P1)   │
│  Medium - 2w │    │   Low - 1w      │
└───┬──────────┘    └─────────────────┘
    │
┌───▼──────────────┐
│ Payment (P0)     │
│  Critical - 4w   │
└───┬──────────────┘
    │
┌───▼──────────┐
│ Checkout     │
│ High - 2w    │
└──────────────┘
```

---

## Feature Matrix

| Feature | Priority | Complexity | Depends On | Blocks | Can Start |
|---------|----------|------------|------------|--------|-----------|
| Authentication | P0 | Medium | None | 8 features | Week 1 |
| Dashboard | P0 | Medium | Auth | Widgets | Week 3 |
| Product Catalog | P0 | High | Auth, DB | Cart, Wishlist | Week 3 |
| Shopping Cart | P0 | Medium | Catalog | Checkout | Week 7 |
| Payment Integration | P0 | Critical | Auth, Cart | Checkout, Billing | Week 9 |
| Checkout | P0 | High | Payment | None | Week 13 |
| Wishlist | P1 | Low | Catalog | None | Week 7 |
| User Profile | P0 | Low | Auth | Settings | Week 3 |
| Settings | P1 | Low | Profile | None | Week 4 |
| ... | ... | ... | ... | ... | ... |

---

## Critical Path Analysis

**Critical Path:** Authentication → Product Catalog → Shopping Cart → Payment Integration → Checkout

**Total Duration:** 15 weeks (60% of project timeline)

### Critical Path Features

1. **Authentication (P0)** - 2 weeks
   - No dependencies
   - **Blocks 8 features**
   - Risk: Medium (complex auth flows)

2. **Product Catalog (P0)** - 4 weeks
   - Depends: Authentication
   - **Blocks 5 features**
   - Risk: High (large dataset, search complexity)

3. **Shopping Cart (P0)** - 2 weeks
   - Depends: Product Catalog
   - Blocks: Payment, Checkout
   - Risk: Low

4. **Payment Integration (P0)** - 4 weeks
   - Depends: Cart, Auth
   - **Blocks 3 features**
   - Risk: High (PCI-DSS compliance, Stripe integration)

5. **Checkout (P0)** - 2 weeks
   - Depends: Payment
   - Blocks: None
   - Risk: Medium (multi-step flow)

⚠️ **Risk:** Any delay in critical path features directly delays project completion.

💡 **Mitigation:**
- Start critical path features first
- Assign senior developers to critical path
- Parallelize non-critical features

---

## Recommended Implementation Phases

### 🚀 Phase 1: Foundation (Weeks 1-4)

**Goal:** Enable parallel development

| Feature | Priority | Complexity | Team | Duration |
|---------|----------|------------|------|----------|
| Authentication | P0 | Medium | Mobile + Backend | 2 weeks |
| Database Schema | P0 | Low | Backend | 1 week |
| API Foundation | P0 | Medium | Backend | 2 weeks |
| Design System | P0 | Low | Design + Mobile | 2 weeks |
| Error Tracking Setup | P0 | Low | DevOps | 1 week |

**Parallel Streams:** 3
- Stream A: Auth (mobile + backend)
- Stream B: Database + API (backend)
- Stream C: Design system (design + mobile)

**Completion:** All features must finish before Phase 2

---

### 🏗️ Phase 2: Core Features (Weeks 5-12)

**Goal:** Build P0 features on critical path

| Feature | Depends On | Team | Start | Duration |
|---------|-----------|------|-------|----------|
| Product Catalog | Auth, API | Mobile + Backend | Week 5 | 4 weeks |
| User Profile | Auth | Mobile | Week 5 | 1 week |
| Dashboard | Auth, Real-time | Mobile + Backend | Week 5 | 3 weeks |
| Shopping Cart | Catalog | Mobile | Week 9 | 2 weeks |
| Search | Catalog | Backend + Mobile | Week 9 | 3 weeks |

**Parallel Streams:** 2-3
- Stream A: Catalog (critical path)
- Stream B: Dashboard + Profile
- Stream C: Search (starts week 9)

---

### 💳 Phase 3: Monetization (Weeks 11-16)

**Goal:** Enable revenue features

| Feature | Depends On | Team | Start | Duration |
|---------|-----------|------|-------|----------|
| Payment Integration | Auth, Cart | Backend + Mobile | Week 11 | 4 weeks |
| Checkout Flow | Payment | Mobile | Week 15 | 2 weeks |
| Order Management | Checkout | Mobile + Backend | Week 17 | 3 weeks |
| Invoices | Payment | Backend | Week 15 | 2 weeks |

**Parallel Streams:** 2
- Stream A: Payment → Checkout (critical path)
- Stream B: Invoices (parallel to checkout)

---

### ✨ Phase 4: Enhancements (Weeks 17-24)

**Goal:** P1 features and polish

| Feature | Depends On | Team | Start | Duration |
|---------|-----------|------|-------|----------|
| Wishlist | Catalog | Mobile | Week 17 | 1 week |
| Product Reviews | Orders | Mobile + Backend | Week 20 | 2 weeks |
| Push Notifications | Auth | Mobile + Backend | Week 17 | 2 weeks |
| Settings | Profile | Mobile | Week 18 | 1 week |
| Analytics Dashboard | Dashboard | Mobile | Week 22 | 2 weeks |

**Parallel Streams:** 4-5 (all P1, no critical path)

---

## Blocking Features Analysis

**Top 5 Blockers:** (Features that block the most others)

1. **Authentication** → Blocks 8 features (Dashboard, Profile, Cart, Payment, etc.)
   - **Impact:** Entire project blocked without this
   - **Action:** Start Week 1, assign senior engineer
   - **Completion Target:** Week 3

2. **Product Catalog** → Blocks 5 features (Cart, Wishlist, Search, Reviews, Checkout)
   - **Impact:** Core e-commerce features blocked
   - **Action:** Start Week 5, full mobile + backend team
   - **Completion Target:** Week 9

3. **Payment Integration** → Blocks 3 features (Checkout, Invoices, Refunds)
   - **Impact:** Revenue features blocked
   - **Action:** Start Week 11, compliance review in parallel
   - **Completion Target:** Week 15

4. **API Foundation** → Blocks 10 features (all backend-dependent features)
   - **Impact:** Frontend can only use mocked data without this
   - **Action:** Start Week 1, backend team
   - **Completion Target:** Week 3

5. **Real-time Infrastructure** → Blocks 3 features (Dashboard, Notifications, Chat)
   - **Impact:** Live features blocked
   - **Action:** Start Week 4, backend specialist
   - **Completion Target:** Week 6

💡 **Strategy:** Complete these 5 blockers ASAP to unblock maximum parallel work.

---

## Parallel Work Opportunities

**Max Concurrent Features:** 5-7 (based on team size)

### High-Value Parallel Streams

**Stream 1: Critical Path (Senior Team)**
- Authentication → Catalog → Cart → Payment → Checkout
- Never block this stream
- Priority: P0 only

**Stream 2: User Experience (Mid-Level Team)**
- User Profile → Settings → Preferences
- Dashboard → Widgets → Analytics
- Can pause for critical path support

**Stream 3: Infrastructure (Backend Specialists)**
- API Foundation → Real-time → Search
- Runs in parallel to all other streams
- Priority: P0 foundation, then P1 enhancements

**Stream 4: Nice-to-Haves (Junior Team)**
- Wishlist → Favorites → Share
- Reviews → Ratings → Comments
- All P1/P2, can deprioritize

---

## Risk Assessment

### High-Risk Dependencies

⚠️ **Payment Integration** (Critical path, 4 weeks)
- **Risk:** PCI-DSS compliance can take longer than expected
- **Impact:** Blocks Checkout, delays revenue
- **Mitigation:**
  - Start compliance review in Week 1
  - Use Stripe for SAQ-A (simplest compliance)
  - Parallel: Build checkout with test mode

⚠️ **Product Catalog** (Critical path, 4 weeks)
- **Risk:** Large dataset performance issues
- **Impact:** Blocks 5 downstream features
- **Mitigation:**
  - Implement pagination early
  - Load test with production data size
  - Consider Algolia for search

⚠️ **Real-time Infrastructure** (Blocks 3 features)
- **Risk:** WebSocket complexity, scaling issues
- **Impact:** Dashboard, Notifications, Chat delayed
- **Mitigation:**
  - Use Firebase Realtime DB (managed service)
  - Fallback to polling if websockets fail
  - Implement retry logic

---

## Dependency Conflicts

**None detected.** ✅

_If circular dependencies existed, they would be listed here with resolution suggestions._

---

## Optimization Recommendations

### 1. Start Critical Path Immediately
**Action:** Begin Authentication and API Foundation in Week 1
**Impact:** Enables 70% of other features to start by Week 3

### 2. Parallelize Non-Dependent Features
**Action:** Build User Profile, Settings, Design System in parallel to Auth
**Impact:** 3 features complete while waiting for Auth → 3 weeks saved

### 3. Mock Dependencies for Early Frontend Work
**Action:** Create mock API responses for Catalog while backend builds real API
**Impact:** Frontend team doesn't block, integration week saved

### 4. Pre-start Compliance Work
**Action:** Begin HIPAA/PCI-DSS audits before features are coded
**Impact:** Compliance doesn't block launch → 2-4 weeks saved

### 5. De-risk Critical Path Early
**Action:** Spike Payment Integration in Week 1 (2-3 days research)
**Impact:** Identify issues before they're on critical path → risk reduced

---

## Team Allocation Suggestions

Based on dependencies and critical path:

**Weeks 1-4 (Foundation):**
- 50% team on critical path (Auth, API)
- 30% on parallel infrastructure (Database, Real-time)
- 20% on design system

**Weeks 5-12 (Core Features):**
- 60% team on critical path (Catalog, Cart)
- 40% on parallel features (Dashboard, Profile)

**Weeks 13-20 (Monetization):**
- 70% team on critical path (Payment, Checkout)
- 30% on nice-to-haves (Wishlist, Reviews)

**Weeks 21-24 (Polish):**
- 100% team on parallel P1 features

---

## Dependencies by Type

### Technical Dependencies (MUST complete in order)
- [Count] features with technical dependencies
- Example: Payment → Checkout

### Logical Dependencies (SHOULD complete in order)
- [Count] features with logical dependencies
- Example: Product → Product Reviews

### Domain Dependencies (NICE TO complete in order)
- [Count] features with domain dependencies
- Example: Offline Sync → Offline Features

### No Dependencies (Can start immediately)
- [Count] features with no dependencies
- Example: Design System, Static Pages

---

## Next Steps

1. **Review & Validate:** Confirm dependencies with technical lead
2. **Adjust Timeline:** Use critical path (XX weeks) for realistic schedule
3. **Assign Teams:** Match senior engineers to critical path features
4. **Create Sprints:** Break phases into 2-week sprints
5. **Track Progress:** Update dependency status weekly
6. **Risk Mitigation:** Address high-risk dependencies first

**Commands:**
- `claude estimate-cost` - Generate budget based on this timeline
- `claude gen-prprompts` - Generate development guides for all features
- `claude bootstrap-from-prprompts` - Start implementation

---

*Generated by Feature Dependency Analyzer v1.0.0*
*Methodology: Technical dependency analysis + Critical path calculation*
*Source: [PRD Path]*
```

### Step 9: Validation & Output

After generating report:

1. **Sanity Checks:**
   - No circular dependencies?
   - Critical path < 80% of timeline?
   - At least 30% of features can start immediately?
   - Blockers identified and flagged?

2. **Output Message:**

```
✅ Generated dependency analysis at docs/FEATURE_DEPENDENCIES.md

🔗 Dependency Summary:
- Total Features: XX
- Can Start Immediately: XX (XX%)
- Critical Path: XX weeks (XX% of timeline)
- Top Blocker: [Feature] (blocks XX features)

🎯 Key Recommendations:
1. Start [Blocker] in Week 1 (unblocks XX features)
2. Parallelize [Feature A], [Feature B], [Feature C]
3. De-risk [High-Risk Feature] with early spike

⚠️ Critical Path Warning:
[Feature] is on critical path. Any delay cascades to:
- [Downstream 1] (Week XX)
- [Downstream 2] (Week XX)
- [Downstream 3] (Week XX)

Next steps:
1. Review dependency graph (Section 2)
2. Validate critical path (Section 3)
3. Run: claude estimate-cost
4. Run: claude gen-prprompts

Start implementation? (y/n)
```

## Notes

- **Use graph visualization:** Mermaid or ASCII art for dependency graph
- **Update during development:** Re-run analysis when PRD changes
- **Consider team size:** More parallel streams require more team members
- **Flag compliance blockers:** HIPAA audits can take 4-8 weeks
- **Mock for parallelism:** Use mock data to unblock frontend while backend builds

## Limitations

- Cannot detect hidden dependencies in code
- Assumes features are accurately described in PRD
- Does not account for external dependencies (third-party APIs)
- Critical path calculation assumes linear dependencies (no OR/XOR logic)