title: MISSE 7 RETRIEVE
duration: 60

steps:
  # Skip the "planned PET" part

  - simo:
    # FYI, "inhibits" basically mean "make sure stuff is turned off before we
    # try to unplug it".
    IV:
      - step: Verify inhibits in place
        substeps:
        - {{CHECKMARK}} Stbd SARJ locked
        - {{CHECKMARK}} MISSE/ELC-2 inhibits

    # This is a simo block that also includes merged columns. Complicated...
    EV1 + EV2:
      - warning: Do not touch the hinged side while closing the MISSE PECs (Pinch Point)
      - caution:
        - Avoid inadverntent contat with the deployed MISSE PECs, which have shatterable materials, and the silver avionics boxes atop the ExPA
        - There isn't a second caution in this block, but I wanted to add one here to show that there could be (also for "warning" and "note" blocks).

  # FIXME: There's an image here that I need to think about how to include

  - simo:

    EV1:
      - step: Translate to S1 Face 2, zenith route
        checkboxes:
        - Fairlead on S0 HR 3467 (bay 1)
      # In 2018 the "GREEN" below would be green-colored text
      - step: Attach '''GREEN''' hook on S1 HR 3208 (bay 17)
        checkboxes:
        - {{CHECKMARK}} Gate closed, hook locked, reels unlocked, release RET
      - step: Translate zenith to ELC-2
        checkboxes:
        - Fairlead on S3 HR 3052 (face 1)
      # there's an icon for a camera here. Not required for now.
      - step: Photograph deployed PECs
        substeps:
        - PEC 7B ({{CHECKMARK}} Ram/Fwd side, {{CHECKMARK}} Aft side)
        - PEC 7A ({{CHECKMARK}} Zenith side, {{CHECKMARK}} Nadir side)
        - {{CHECKMARK}}{{CHECKMARK}} Overall View (2 angles)

    EV2:
      - step: Translate to S1 Face 6, nadir route
      - step: Attach '''GREEN''' hook on S1 HR 3217 or Xo 5790 (bay 17)
        checkboxes:
          - Gate closed, hook locked, reels unlocked, release RET
      - step: Translate outbd to bay 19
      - step: Stow CETA ORU bag on S3 HRs 3046, 3038
      - step: Translate zenith to ELC2

  - EV2:
    - step: If EV1 complete with photos of PEC 7B, close PEC 7B
      checkboxes:
        - All 4 PIP pins are re-installed
    - step: Disconnect connector from PEC 7B
      checkboxes:
        - RET, remove cap from dummy connector J7B
        - Demate connector from PEC
        - Mate connector to dummy connector J7B ({{CHECKMARK}} no FOD, pins)
        - Install cap onto PEC 7B

  - simo:

    EV1:
      - step: Close PEC 7A
        checkboxes:
          - {{CHECKMARK}} All 4 PIP pins are re-installed
    EV2:
      - step:
      - step: Disconnect connector from PEC 7A
        checkboxes:
          - RET, remove cap from dummy connector J7A
          - Demate connector from PEC
          - Mate connector to dummy connector J7A ({{CHECKMARK}} no FOD, pins)
          - Install cap onto PEC 7A

  # Here I haven't put a "step" under EV2, but there is the "checkboxes". If
  # this needs to be changed to the following, that's fine:
  #  - EV2:
  #    - step: Text of the step...
  #      checkboxes:
  #        - Text of the checkbox
  - EV2: Release PEC 7B (2 PIP pins), stow on BRT w/RET (nadir HR)
    checkboxes: Reinstall Socket PIP pins (2)

  - EV2:
   - step: Release PEC 7A (release 2 PIP pins), stow on BRT w/RET (RAM HR)
     checkboxes:
       - Reinstall Socket PIP pins (2)

  - EV1 + EV2:
    - caution: When translating around fwd edge of Node 2 and PMA2, avoid contact with Shuttle


  # FIXME: Need to insert an image here.

  - simo:

    EV1:
      - step: Retrieve GREEN hook from S1 HR 3208
        checkboxes: Gate closed, hook locked, reels unlocked, release RET
      - step: Translate to Node 2, along port/zenith
      - step: Attach GREEN hook on Node 2 HR 0344
        checkboxes: Gate closed, hook locked, reels unlocked, release RET

      - header: STOW MISSE 7A IN PLB
        time: 00:10

      - step: Translate to Orbiter, port, bay 4
      - step: Remove SWC latch PIP pins (2)
      - step: Release latch (2) from stow position
      - step: Stow PEC 7A in carrier (HRs out, Probe up)
      - step: Lock fwd latch in landing config
        checkboxes: Install PIP pin
      - step: Retrieve RET
      - step: Lock aft latch in landing config
        checkboxes: Install PIP pin

    EV2:
      - step: Retrieve GREEN hook from S1 HR 3217 or Xo 5790
        checkboxes: Gate closed, hook locked, reels unlocked, release RET
      - step: Translate to Node 2, stbd/zenith route
        checkboxes:
          - Fairlead on Lab HR 0247 with wrist Adj
          - Fairlead on Node 2 HR 0314
          - Face toward Col and Node 2
      - warning: Stay  2 ft from exposed EFGF connector when OBSS berthed, powered, and EFGF not grappled

      # It'd be better if there was a way to tie this time into the overall
      # time for the whole task, so it wasn't possible to make sub-headings
      # have times that don't add up to the whole task's time.
      - heading: STOW MISSE 7B IN PLB
        time: 00:15

      - step: Translate to Orbiter, stbd, bay 4
      - step: Remove SWC latch PIP pins (2)
      - step: Release latch (2) from stow position
      - step: Stow PEC 7B in carrier (HRs out, Probe up)
      - step: Lock aft latch in landing config
        checkboxes: Install PIP pin
      - step: Retrieve RET
      - step: Lock fwd latch in landing config
        checkboxes: Install PIP pin

  - simo:

    EV1:
      - step: Glove and Gauntlet check
      - step: Translate aft to Bay 9 - MISSE 8 Retrieve

    EV2:
      - step: Glove and Gauntlet check
      - step: Translate aft to S3 Face 1 - S3 CETA Light Install